For the new CEF Date, IT and Marketing Centre the architects Faulkner Brown wanted a “technologically cutting-edge building”

A kit of parts approach was taken and 90nr DELTABEAM®s were incorporated into the design along with Peikko Column Shoes & Anchor bolts. DELTABEAM® Composite Beams providing a slim floor and flat soffit also interfaced with precast floor units which incorporated combined heating & cooling system, creating a Thermally Active Building System (TABS). The frame was delivered the 11-week contractual period.

The new CEF headquarters also secured the 2019 RIBA Northeast Building of the Year Award.

阅读更多 down-arrow.png

项目概览

项目规模:
2100 m2
楼层:
2
开发商:
CEF Ltd
施工单位:
PCE Ltd
结构设计师:
Curtins
建筑师:
FaulknerBrowns
交付年份:
2016
完成时间:
2017