Wang Noi Gas Compressor Station, Ayutthaya, 泰国

  • 建筑类型:
  • 工业建筑
全屏地图 关闭

PTT Public Company Ltd develops new gas compressor station in Ayutthaya, about 70 km north from Bangkok. Gas turbine driven compressors with shaft power of 16 MW used in the project will provide additional capacities of 800 MMSCFD gas for Bangkok city.

Peikko delivered Bolted column connections for precast columns of integrated control & electrical substation building and workshop/warehouse building in the project. Peikko HPKM® Column Shoes and HPM® Anchor Bolts were used in the project.

Peikko Bolted column connection is mechanical connection, which allows column erection with a small crew on site and no temporary bracing is needed. As soon as the nuts are tightened, the connection is moment-resistant and the crane can move on to the next column. Once grouted, a bolt connection is as stiff as a cast in-situ connection. With Peikko system erection of columns is faster and easier compare to conventional ways.

阅读更多 down-arrow.png

项目概览

开发商:
PTT Public Company Limited
施工单位:
Samsung Engineering (Thailand) Co., Ltd
构件生产商:
Advance Prefab Company Limited
交付年份:
2017
完成时间:
2018

我们提供的解决方案

联系我们

Triaskin Dmytro

Triaskin Dmytro

亚太区销售及业务发展经理

APAC Sales & Business Development Manager

手机+65 8809 0173
[email protected]